That long-awaited resurfacing of Warwick Avenue is delayed again – until March 2015 – but this time there is an excuse! I have been lobbying for this seriously overdue and much-needed repair work for years, and am very glad that it is finally going ahead. The repairs had been planned for the end of 2014, but when cores were taken from the concrete slabs that make up the road, it was discovered that they had metal reinforcement, making hopes of using an in-situ recycling technique impossible. I am now told that the SCC contractors, KMG, will be bringing in a specialist surfacing contractor to remove any asphalt on the slabs, repair the slab joints and lay high density asphalt overlay